![]() ![]() ![]() HOMER says the City of Santa Cruz had concerns about resiliency and safety and did not want the generator to be the primary power source for the facility. Using HOMER Pro modeling, Ageto Energy was able to determine the optimal generator size and produce reports to demonstrate to city officials during the design phase that the generator would only need to run 200-300 hours per year, specifically during prolonged periods of cloudy winter weather.